After overcoming various adversities and long stages of testing and trials, the first unit of the Rooppur Nuclear Power Plant is preparing for trial connection to the national grid.
If everything goes well, the electricity generated by this unit may be connected to the national grid experimentally for a few hours today. At that time, there are plans to supply a maximum of 240 megawatts of electricity to the grid.
Dr Khalequzzaman, Deputy Project Director of the project, has announced the plan to experimentally connect electricity to the national grid.
He said that connecting to the national grid does not mean commercial electricity supply will begin.
According to project-related sources, during the experimental connection, a maximum of 240 megawatts of electricity from the first unit may be supplied to the national grid for a few hours.
After that, the connection will be disconnected from the grid and the necessary tests and trials of the power plant will be carried out. If everything goes well, it will be reconnected to the grid with the final approval of the Bangladesh Atomic Energy Regulatory Authority (BAERA), sources said.
Several officials associated with the project, speaking on condition of anonymity, said that the capability verification and testing of the reactor, turbine, and other important equipment have already been successfully completed.
According to their plan, the goal is to finally connect the electricity of Rooppur's first unit to the national grid on November 21. The relevant departments have been informed about this. However, before the final connection, a temporary experimental connection will be given to identify possible faults or complications.
Heat energy generated from nuclear fuel will produce steam from water. The steam will drive the turbine, which will generate electricity. Initially, the power plant will be operated at only 3 percent capacity.
Later, when the generation capacity is increased in phases to 25 to 30 percent, it will be possible to supply regular electricity to the national grid.
At this stage, about 300 megawatts of electricity can be obtained.
Even after this, various types of safety, technical, and capability verification tests will continue. It may take another five to six months to increase production and reach full capacity. Commercial production will begin after the experimental electricity supply phase is completed.
Source: BSS