The ninth and final consignment of nuclear fuel brought from Russia for the country’s first nuclear power plant at Rooppur in Ishwardi, Pabna, has arrived at the project site.
The convoy carrying the nuclear fuel entered the Rooppur Nuclear Power Plant premises in Ishwardi at 5:48 a.m. on Friday, November 27.
Earlier, the convoy departed from Hazrat Shahjalal International Airport in Dhaka for the Rooppur Nuclear Power Plant around 1:00 a.m. on Thursday night, November 26.
With this delivery, a total of nine shipments of uranium nuclear fuel flown to Dhaka from Russia this year have been transported to the Rooppur plant. Previous batches were also brought to Dhaka from Russia via special cargo flights and moved by road under strict security.
According to relevant sources, the nuclear fuel was transported by road to Rooppur under tight security supervised by the Bangladesh Army, with support from the Special Security and Protection Battalion (SPBn), police, and other law enforcement agencies.
Extensive security measures were put in place along the route from Dhaka to Rooppur across the respective districts, and all vehicular and public movement along the roads was restricted to ensure the convoy's uninterrupted passage to the project area.
Notably, the first unit of the Rooppur Nuclear Power Plant has already supplied electricity to the national grid on a trial basis twice and is currently in the pre-commercial generation phase.
On November 23 at 10:20 a.m., the first unit was synchronized with the national grid for the second trial run, successfully supplying power continuously for nearly 30 hours.
The estimated value of the electricity supplied to the grid during this period was around Tk7.06 crore. Supply to the grid was halted at 5:05 p.m. on Tuesday, November 24.
According to national transmission line sources, the first unit of Rooppur consistently supplied about 320 megawatts of electricity to the national grid during the second phase.
Plant officials said that although the second trial run was initially scheduled to last 10 to 24 hours, it continued beyond the planned timeframe for nearly 30 hours.
Project officials described the achievement as a significant milestone in Bangladesh’s nuclear power journey, as well as a notable accomplishment for the Nuclear Power Plant Company Bangladesh Limited (NPCBL) in terms of operational capacity and technical preparedness.
They added that following the successful second trial run, the unit was disconnected from the national grid.
Engineers are currently analyzing various operational parameters, turbine-generator systems, and the performance of related equipment recorded during power generation.
Subsequent operational steps will be determined based on the findings of these assessments.
Earlier, the first unit of the Rooppur Nuclear Power Plant was connected to the national grid for its first trial run at 3:16 p.m. on November 17.
According to project sources, full-scale commercial electricity generation from the first unit will begin once the trial operations conclude successfully.
The project tenure has been extended until June 2028, with the estimated cost standing at Tk1,38,686 crore.
Combined, the plant’s two units have a total generation capacity of 2,400 megawatts (1,200 megawatts each). Once operating at full capacity, the plant is expected to add at least 2,060 megawatts of electricity to the national grid.