The Rooppur Nuclear Power Plant has begun supplying electricity to the national grid on an experimental basis for the second time.
Power transmission commenced at 10:20 am on Monday (November 23).
Saikat Ahmed, Senior Scientific Information Officer and Media Focal Point of the Rooppur Nuclear Power Plant Construction Project, confirmed the development in a press release.
Project Director Dr. Md. Kabir Hossain said approximately 300 to 350 megawatts of electricity will be supplied to the national grid on a trial basis for 10 to 24 hours during this phase.
Necessary technical tests of the plant's generation system and its synchronized operation with the national grid will be conducted during this period.
Earlier, on November 17, 2026, at 3:16 pm, the Rooppur Nuclear Power Plant began supplying around 350 megawatts of electricity to the national grid on an experimental basis for the first time.
Today's synchronization marks the continuation of those grid integration trials.